M20- SAW CUTTING & JOINT SEALING

Shepherd and Sons

Scope

THE WORKS WERE CARRIED OUT ON THE M20, BETWEEN JUNCTIONS 8 AND 9 (COASTBOUND), COVERING APPROXIMATLRY 20 KILOMETERS OF CONCRETE CARRIGEWAY.

Shepherd and Sons

PROCESS

STEP 1 : PLOUGHING OUT OLD SEALANT

STEP 2: SAWING

STEP 3: DRYING

STEP 4: GRIT BLASTING

STEP 5 : CAULKING

STEP 6 : SEALING

Shepherd and Sons

COLLABORATORS

FOR THIS PROJECT, WE PARTERNED WITH ROADTEACHS and PG SWEEPERS TO DELIVER WORKS ON BEHALF OF NATIONAL HIGHWAYS ENGLAND.

Shepherd and Sons

STATS

TOTALM SHIFTS – 20 NIGHT SHIFTS (WORKING WINDOW 10PM – 3;30 AM)
 
TOTAL METERS CUT AND SEALED – 23,304 LnM
 
AVERAGE CUT AND SEAL PER SHIFT – 1,165.2LnM